Deadlines
Every open claim that carries a date the company promised something by, soonest first. Dates already past are still listed - a missed deadline is the point, not an omission.
1,018 total · showing 701–800
- Riot - Anthropic data center full 191 MW deployment stated · promised 2028-06-30 · stated 2026-08-13
- Riot - Anthropic 191 MW data center lease stated · promised 2028-06-30 · stated 2026-08-20
- Riot - Rockdale full deployment (191MW) stated · promised 2028-06-30 · stated 2026-08-20
- Hut 8 - Beacon Point data hall expansion stated · promised 2028-06-30 · stated 2026-09-01
- Applied Digital - Delta Forge 2 contracted revenue and delivery stated · promised 2028-06-30 · stated 2026-09-01
- Applied Digital - High Investment Grade Hyperscaler Delta Forge 1 lease stated · promised 2028-06-30 · stated 2026-09-01
- Hut 8 - Beacon Point data hall expansion stated · promised 2028-06-30 · stated 2026-09-01
- Hut 8 - Beacon Point Phase 2 data hall delivery Q2 2028 stated · promised 2028-06-30 · stated 2026-09-01
- TeraWulf - Initial 500 MW capacity delivery targeted for H2 2028 stated · promised 2028-07-01 · stated 2026-05-25
- Applied Digital - Data center build capacity delivery commitment stated · promised 2028-09-03 · stated 2026-09-03
- CoreWeave - Convertible Notes Earliest Redemption Date stated · promised 2028-12-05 · stated 2025-12-10
- Core Scientific - AMD Capacity Reservation Option stated · promised 2028-12-28 · stated 2026-07-27
- TeraWulf - Muskie campus 500 MW capacity by H2 2028 stated · promised 2028-12-31 · stated 2026-08-21
- Core Scientific - Megawatt delivery rate guidance stated · promised 2028-12-31 · stated 2026-08-31
- Applied Digital - Contracted capacity planned for delivery by 2028 stated · promised 2028-12-31 · stated 2026-08-20
- Core Scientific - AMD full 530 MW delivery stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - Cayuga Phase 2 stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - Cayuga Phase II expansion stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - Exclusive Fluidstack JV options for future capacity stated · promised 2028-12-31 · stated 2026-09-01
- TeraWulf - Muskie Phase I Capacity stated · promised 2028-12-31 · stated 2026-09-01
- Cipher Mining - McLennan energization target stated · promised 2028-12-31 · stated 2026-02-23
- Cipher Mining - Mikeska energization target stated · promised 2028-12-31 · stated 2026-02-23
- Applied Digital - Polaris Forge 3 hyperscaler leases 300 MW stated · promised 2028-12-31 · stated 2026-09-01
- Cipher Mining - Colchis energization target stated · promised 2028-12-31 · stated 2026-02-23
- Applied Digital - Polaris Forge 3 delivery and contracted revenue stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - High Investment Grade Hyperscaler Polaris Forge 3 lease stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Total AI data center capacity stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Majority of capacity online by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - 1,410 MW backlog by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Contracted data center capacity delivery completion stated · promised 2028-12-31 · stated 2026-08-28
- Applied Digital - Polaris Forge 3 contracted capacity and revenue stated · promised 2028-12-31 · stated 2026-07-28
- Applied Digital - Contracted lease portfolio as of May 31, 2026 stated · promised 2028-12-31 · stated 2026-07-28
- Cipher Mining - Mikeska energization target stated · promised 2028-12-31 · stated 2026-02-23
- Core Scientific - Multi-campus deployments through 2028 stated · promised 2028-12-31 · stated 2026-07-28
- CoreWeave - Indonesia Greater Jakarta AI compute deployment stated · promised 2028-12-31 · stated 2026-08-06
- TeraWulf - Muskie Data Campus 500 MW capacity by H2 2028 stated · promised 2028-12-31 · stated 2026-08-21
- Core Scientific - Expected power delivery rate through 2028 stated · promised 2028-12-31 · stated 2026-08-31
- Applied Digital - Data center capacity delivery completion stated · promised 2028-12-31 · stated 2026-08-28
- Core Scientific - 2028 AI colocation dedication target stated · promised 2028-12-31 · stated 2026-09-01
- Hut 8 - Texas facility expected operating income in 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Backlog capacity by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Expected capacity by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Polaris Forge 3 contracted revenue and delivery stated · promised 2028-12-31 · stated 2026-09-01
- Marathon Digital - RSU Vesting Schedule stated · promised 2028-12-31 · stated 2026-02-24
- Cipher Mining - Colchis energization target stated · promised 2028-12-31 · stated 2026-02-23
- Cipher Mining - McLennan energization target stated · promised 2028-12-31 · stated 2026-02-23
- Cipher Mining - Colchis AEP interconnection agreement targeting energization stated · promised 2028-12-31 · stated 2026-02-23
- Cipher Mining - McLennan site energization target stated · promised 2028-12-31 · stated 2026-02-23
- Cipher Mining - Mikeska site energization target stated · promised 2028-12-31 · stated 2026-02-23
- Applied Digital - 1,410 MW capacity backlog by 2028 stated · promised 2028-12-31 · stated 2026-09-01
- Hut 8 - Texas facility fully operational stated · promised 2028-12-31 · stated 2026-09-01
- Applied Digital - Base Electron power capacity arrival in 2029 stated · promised 2029-01-01 · stated 2026-09-03
- Applied Digital - Base Electron natural gas generation partnership stated · promised 2029-01-01 · stated 2026-09-03
- Core Scientific - Miner Equipment Lender Facility - 80% of allowed claims stated · promised 2029-01-23 · stated 2024-01-24
- Core Scientific - Secured Convertible Notes - $260M, maturing 2029 stated · promised 2029-01-23 · stated 2024-01-24
- Core Scientific - Tranche 2 Warrants - 82.0M at $0.01 exercise price stated · promised 2029-01-23 · stated 2024-01-24
- Core Scientific - Miner Equipment Lender Facility stated · promised 2029-01-23 · stated 2024-01-22
- Core Scientific - Secured Convertible Notes stated · promised 2029-01-23 · stated 2024-01-22
- Core Scientific - Tranche 2 Warrants stated · promised 2029-01-23 · stated 2024-01-22
- Core Scientific - Tranche 2 Warrant Authorization stated · promised 2029-01-23 · stated 2024-02-19
- WhiteFiber - Company may redeem notes starting February 6, 2029 stated · promised 2029-02-06 · stated 2026-01-25
- Core Scientific - Portfolio conversion to HDC within 3 years stated · promised 2029-03-01 · stated 2026-03-01
- Core Scientific - Convert all MW to HDC over three years stated · promised 2029-03-01 · stated 2026-03-01
- Core Scientific - HDC conversion strategy stated · promised 2029-03-01 · stated 2026-03-01
- WhiteFiber - Duke Energy NC-1 capacity commitment stated · promised 2029-05-16 · stated 2026-03-25
- WhiteFiber - Duke Energy 99 MW service target for NC-1 stated · promised 2029-05-16 · stated 2026-03-25
- WhiteFiber - Duke Energy Capacity Agreement for NC-1 stated · promised 2029-05-16 · stated 2026-03-25
- WhiteFiber - Duke Energy capacity agreement for NC-1 stated · promised 2029-05-16 · stated 2025-08-07
- WhiteFiber - Duke Energy capacity commitment - 99 MW milestone stated · promised 2029-05-16 · stated 2025-07-31
- WhiteFiber - Duke Energy capacity agreement - Phase 3 stated · promised 2029-05-16 · stated 2025-07-28
- WhiteFiber - Duke Energy - 99 MW stated · promised 2029-05-16 · stated 2025-07-22
- WhiteFiber - Duke Energy 99 MW capacity commitment stated · promised 2029-05-16 · stated 2025-07-10
- WhiteFiber - NC-1 conditional purchase price increase (per-MW over 99 MW threshold) stated · promised 2029-05-20 · stated 2026-03-25
- Applied Digital - Secured revolving credit facility stated · promised 2029-05-28 · stated 2026-06-25
- Applied Digital - $550M revolving credit facility stated · promised 2029-05-31 · stated 2026-09-01
- Applied Digital - $550M Revolving Credit Facility stated · promised 2029-05-31 · stated 2026-09-01
- Applied Digital - $550 million revolving credit facility stated · promised 2029-05-31 · stated 2026-09-01
- Nebius - 2.00% Convertible Notes due 2029 stated · promised 2029-06-05 · stated 2025-09-11
- Nebius - 2029 convertible notes maturity obligation stated · promised 2029-06-05 · stated 2025-06-01
- Hut 8 - Convertible Note Initial Maturity Term stated · promised 2029-06-21 · stated 2024-06-23
- Core Scientific - Three-year timeline to exit Bitcoin mining stated · promised 2029-08-22 · stated 2026-08-22
- Core Scientific - $460 million senior unsecured convertible notes stated · promised 2029-09-01 · stated 2026-09-01
- Core Scientific - August 2024 senior unsecured convertible note stated · promised 2029-09-01 · stated 2026-09-01
- Cipher Mining - Optional noteholder repurchase date for convertible notes stated · promised 2029-10-01 · stated 2025-09-30
- IREN - Convertible Notes Interest Rate and Maturity stated · promised 2029-12-15 · stated 2025-06-12
- Core Scientific - Hunt County power energization schedule stated · promised 2029-12-31 · stated 2026-09-01
- Applied Digital - Largest state taxpayer by 2029 stated · promised 2029-12-31 · stated 2026-08-29
- Applied Digital - Annual property tax payments by 2029 stated · promised 2029-12-31 · stated 2026-08-29
- TeraWulf - Cayuga Phase 3 stated · promised 2029-12-31 · stated 2026-09-01
- TeraWulf - Cayuga Phase III expansion stated · promised 2029-12-31 · stated 2026-09-01
- TeraWulf - Cayuga total buildout capacity stated · promised 2029-12-31 · stated 2026-09-01
- TeraWulf - Cayuga site phased capacity expansion stated · promised 2029-12-31 · stated 2026-09-01
- TeraWulf - Lake Hawkeye Campus Capacity stated · promised 2029-12-31 · stated 2026-09-01
- Hut 8 - 2029 revenue projection stated · promised 2029-12-31 · stated 2026-08-30
- Hut 8 - 2029 earnings projection stated · promised 2029-12-31 · stated 2026-08-30
- Cipher Mining - Milsing energization target stated · promised 2029-12-31 · stated 2026-02-23
- Cipher Mining - Milsing energization target stated · promised 2029-12-31 · stated 2026-02-23
- Cipher Mining - Milsing site energization target stated · promised 2029-12-31 · stated 2026-02-23
- CleanSpark - 2029 revenue projection stated · promised 2029-12-31 · stated 2026-09-04
- CleanSpark - 2029 earnings projection stated · promised 2029-12-31 · stated 2026-09-04