Q4 2025 Lake Mariner power cost

Company: TeraWulf

Subject kind
guidance
Statement date
2025-11-10
Promised by
2025-12-31
Promised amount
0.05 USD/kWh
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No Q4-only power cost is reported. Subtracting nine-month from full-year figures gives an implied ~$0.063/kWh for Q4 2025, above the $0.05 estimate, but that is a derived number and covers mining facilities generally.

“Total energy expense, net of expected demand response proceeds (5) ($ in thousands) $ 16,835 $ 16,899 $ 63,482 $ 49,226 Cost per kWh $ 0.047 $ 0.038 $ 0.059 $ 0.039”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“Cost per kWh $ 0.060 $ 0.043 Energy expense, net as % of value of bitcoin mined 52.9 % 40.1 %”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Estimated power cost of $0.05/kWh at Lake Mariner for Q4 2025.

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Estimated power cost of $0.05/kWh at Lake Mariner for Q4 2025”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

A footnote to the cash cost to mine table states an estimated power cost of $0.05/kWh at Lake Mariner for Q4 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_26c9692236622f11a71632d61560402c/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Estimated power cost of $0.05/kWh at Lake Mariner for Q4 2025”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2025-11-10.