North Dakota AI data center power timeline
Company: Applied Digital
What the later record shows
Partly delivered · happened November 30, 2025
The first 100 MW HPC building (ELN-02) at the Polaris Forge 1 campus in Ellendale, ND was fully energized during the six months ended November 30, 2025. By April 2026 the campus still showed only 100 MW energized, with 300 MW under construction, so the 200 MW scope was only partly powered in 2025.
“We recently commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, ND”
2025-12-04 · Applied Digital S-3 filed 2025-12-05 View cached copy (2026-08-31)Live source ↗
“ELN-02 at Polaris Forge 1 fully energized during the six months ended November 30, 2025”
2026-01-07 · Applied Digital 10-Q filed 2026-01-08 View cached copy (2026-08-31)Live source ↗
“PF1- Polaris Forge 1 - CoreWeave Ellendale, North Dakota • 400 MW Contracted • 100 MW Energized • 300 MW Under Construction”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗
Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Power for the AI data center under construction in North Dakota (200MW for AI) is estimated to arrive in 2025.
Source (primary)
applied-digital 8-K exhibit (applieddigital-investorp.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-14)Live source ↗
Quote: “Construction has started on our AI data center Power Timeline: Estimated in 2025”
How we checked this
Checked on November 16, 2026. The cited source supports part of this claim, but not all of it.
The presentation gives a 2025 power estimate for the AI data center under construction and lists 200MW for AI in North Dakota, but in the map slide's flattened text the 2025 timeline is not clearly tied to the North Dakota site rather than another location.
Confirmed in the source:
- Construction has started on Applied Digital's AI data center
- Power for an Applied Digital AI data center under construction is estimated for 2025
- Applied Digital's North Dakota (Jamestown & Ellendale) sites include 200MW for artificial intelligence
We could not confirm this from the cited source:
- That the 2025 power timeline refers specifically to the North Dakota 200MW AI facility
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000012/applieddigital-investorp.htm) in full (14,133 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (applieddigital-investorp.htm)
Quote: “Construction has started on our AI data center Power Timeline: Estimated in 2025”