What the later record shows
Partly delivered
MTL-3 (7 MW) became operational in November 2025, but total capacity online in 2025 was about 11 MW rather than ~16 MW. MTL-2 (5 MW) was not yet online.
“The facility has been retrofitted to Tier-3 standards and was completed and operational in November 2025.”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
“MTL-1 4.0 MW MTL-3 7.0 MW NC-1(5) 99.0 MW Footprint Pipeline(3) MTL-2 5.0 MW(2) ~11 MW Online in 2025”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
“MTL-2 5 Gross MW Capacity: TBD Customer: TBD IT Load: 3 MW Average Term: TBD”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Company expects to add 12 MW (gross) of capacity inclusive of MTL-2 and MTL-3 sites for total capacity of approximately 16 MW (gross) by end of 2025
Source (primary)
WhiteFiber S-1/A filed 2025-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The prospectus states the company expects to add 12 MW (gross), including MTL-2 and MTL-3, for total capacity of about 16 MW (gross) by the end of 2025.
Confirmed in the source:
- The company expects to add 12 MW (gross) of capacity
- The added capacity is inclusive of the MTL-2 and MTL-3 sites
- Total capacity is expected to be approximately 16 MW (gross)
- The target is the end of 2025
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025068434/ea0249945-03.htm) in full (841,778 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-07-29
Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”