2025 year-end total capacity target

Company: WhiteFiber

Subject kind
guidance
Statement date
2025-07-31
Promised by
2025-12-31
Promised amount
16.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

About 11 MW gross was online in 2025 versus the ~16 MW target. MTL-3 is operational, but MTL-2 development was put on hold.

“MTL-2 5.0 MW(2) ~11 MW Online in 2025 ~76 MW Online by YE 2026E”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
“(2) Development of MTL-2 has been put on hold. (3) Pipeline defined as data center sites”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Expect to add 12 MW gross capacity inclusive of MTL-2 and MTL-3 sites for total capacity of approximately 16 MW gross by end of 2025

Source (primary)

WhiteFiber S-1/A filed 2025-08-01 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The prospectus summary states that the company expects to add 12 MW (gross), including MTL-2 and MTL-3, for a total of about 16 MW (gross) by the end of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025070709/ea0249945-04.htm) in full (845,158 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1/A filed 2025-08-01

Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.