910MW total data center capacity by end-2025

Company: IREN

Subject kind
facility capacity
Statement date
2025-01-20
Promised by
2025-12-31
Promised amount
910.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

810MW was operating at June 30, 2025, and the remaining Childress capacity (Horizon 1) was still under construction. No passage shows 910MW reached.

“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0 Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN expects its data center portfolio to total 910MW by the end of 2025, with planning underway so all of it can accommodate liquid-cooled GPUs.

Source (primary)

iren 8-K exhibit (ny20037451x2_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-21)Live source ↗

Quote: “accommodate advanced liquid-cooled GPUs across all IREN data centers (910MW by the end of 2025)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ny20037451x2_ex99-1.htm)

Quote: “accommodate advanced liquid-cooled GPUs across all IREN data centers (910MW by the end of 2025)”

View cached copy (2026-10-21)Live source ↗

Record of changes

October 21, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 21, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.