250 MW billable colocation by end of 2025
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
October 2025 materials still describe 250 MW by end of 2025 as a target, with ~120+ MW energized. No passage reports the year-end outcome.
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core Scientific is on track to deliver 250 MW of billable high-density colocation capacity by the end of 2025.
Source (primary)
First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “On track to deliver 250 MW by the end of 2025”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The presentation states it is on track to deliver 250 MW by end of 2025, and the slide's timeline shows billable colocation capacity reaching 250 MW in Q4.
Confirmed in the source:
- Core Scientific states it is on track to deliver 250 MW by the end of 2025
- The 250 MW refers to billable high-density colocation capacity, shown on the quarterly delivery timeline that follows the slide
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11247/pdf/First+Quarter+Fiscal+Year+2025+Earnings+Presentation.pdf) in full (28,649 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “On track to deliver 250 MW by the end of 2025”