jain.com

32 EH/s cumulative hashrate target by end of 2025

Company: Cipher Mining

Subject kind
guidance
Statement date
2022-03-03
Promised by
2025-12-31
Promised amount
32.0 EH/s
Current status
outcome unconfirmed

What the later record shows

Partly delivered

The Q3 2025 update shows operating hashrate of ~11.3 EH/s (Odessa), ~10.1 EH/s (Black Pearl) and ~4.4 EH/s (JV sites), about 26 EH/s in total. No passage shows the ~32 EH/s target reached.

“477 MW Operating Capacity Including JV Capacity CURRENT OPERATIONS ~16.8 EH/s Q2 2025 ~23.5 EH/s Q3 2025”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“150 MW Total Operating Power Capacity ~13.9 J/TH Fleet Efficiency ~10.1 EH/s Total Operating Hashrate”
2025-11-02 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-09-27)Live source ↗

Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

By end of 2025, potential to reach cumulative hashrate of approximately 32 EH/s

Source (primary)

Cipher Mining 10-K filed 2022-03-04 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “by the end of 2025, we will have the potential to reach a cumulative electrical power capacity of approximately 745MW and corresponding hashrate of approximately 32 EH/s”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The 10-K gives the approximately 32 EH/s hashrate potential by end of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000095017022002861/cifr-20211231.htm) in full (509,143 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2022-03-04

Quote: “by the end of 2025, we will have the potential to reach a cumulative electrical power capacity of approximately 745MW and corresponding hashrate of approximately 32 EH/s”

View cached copy (2026-09-27)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 28, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.