Black Pearl site online in 2025
Company: Cipher Mining
What the later record shows
Partly delivered
Black Pearl Phase I (150 of 300 MW) was energized and mining by August 2025. Phase II was not brought online in 2025: the site was retrofitted for HPC, and its first HPC capacity was delivered only in August 2026, with the rest still under construction.
“Black Pearl Phase I o Construction and energization successfully completed with ~6.9 EH/s currently deployed”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“Black Pearl data center continues to progress towards completion with remaining Phase I data halls moving through MEP fit-out and Phase II concrete foundations”
2026-08-03 · cipher-mining 8-K exhibit (q226_earningsxprxdraftxvf.htm) View cached copy (2026-09-02)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cipher aims to bring the Black Pearl front-of-the-meter site, with interconnection of up to 300 MW, online in 2025.
Source (primary)
cipher-mining 8-K exhibit (cifr-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Black Pearl is a front-of-the-meter site that we aim to bring online in 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (cifr-ex99_1.htm)
Quote: “Black Pearl is a front-of-the-meter site that we aim to bring online in 2025.”