~270 MW HPC infrastructure for CoreWeave by H2 2025
Company: Core Scientific
What the later record shows
Partly delivered
In October 2025 the company reported about 120+ MW energized at Denton and Marble, and it described 250 MW (not ~270 MW) by end-2025 as its target. No later passage confirms the full ~270 MW was delivered.
“~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress Precast Building Completed at Dalton 1 & Muskogee Sites”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-10-16)Live source ↗Archive.org ↗
Checked November 2, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Combined with the previously announced 200 MW, the agreement positions Core Scientific to provide approximately 270 MW of HPC infrastructure to CoreWeave by the second half of 2025.
Source (primary)
core-scientific 8-K exhibit (ex991-finalcorzhpcoptionre.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-02)Live source ↗
Quote: “the agreement announced today will position Core Scientific to provide approximately 270 MW of HPC infrastructure to CoreWeave by the second half of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (ex991-finalcorzhpcoptionre.htm)
Quote: “the agreement announced today will position Core Scientific to provide approximately 270 MW of HPC infrastructure to CoreWeave by the second half of 2025”