Partly delivered
Only about 11 MW was online in 2025, against the ~16 MW guidance. MTL-3 was delivered in November 2025, while MTL-2's 5 MW was still pending in June 2026.
“The facility has been retrofitted to Tier-3 standards and was completed and operational in November 2025.”
2026-03-25 · WhiteFiber 10-K filed 2026-03-26 View cached copy (2026-08-31)Live source ↗
“MTL-1 4.0 MW MTL-3 7.0 MW NC-1(5) 99.0 MW Footprint Pipeline(3) MTL-2 5.0 MW(2) ~11 MW Online in 2025”
2026-06-09 · whitefiber 8-K exhibit (ea029430601ex99-1.htm) View cached copy (2026-09-06)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Expects to add 12 MW (gross) of capacity by end of 2025 (inclusive of MTL-2 and MTL-3) for total capacity of approximately 16 MW (gross)
Source (primary)
WhiteFiber S-1/A filed 2025-07-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The prospectus states that the company expects to add 12 MW (gross) of capacity, including MTL-2 and MTL-3, for a total of about 16 MW (gross) by the end of 2025.
Confirmed in the source:
- WhiteFiber expects to add 12 MW (gross) of capacity by the end of 2025
- The expected 12 MW (gross) addition includes the MTL-2 and MTL-3 sites
- Expected total capacity is approximately 16 MW (gross) by the end of 2025
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025066839/ea0249945-s1a1_white.htm) in full (824,020 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber S-1/A filed 2025-07-23
Quote: “We are aggressively pursuing our development pipeline and expect to add 12 MW (gross) of capacity, inclusive of the MTL-2 and MTL-3 sites, for total capacity of approximately 16 MW (gross), by the end of 2025.”