Black Pearl Facility

Project of Cipher Mining

Kind
datacenter
Location
11786 County Road 209, Wink, TX 79789
County
Winkler County
State/region
TX
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook300 MW2026-02-23Amazon 15-year Black Pearl lease
Under construction300 MW2026-08-03Black Pearl Facility capacity
Permitted--
Interconnect approved utility has agreed to deliver300 MW2023-11-07Black Pearl ERCOT power approval
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2026-02-23Black Pearl facility gross capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2026-02-23
Amazon Web Services - tenant · 300 MW · 15-year term source

Claims about this project

2023-11-07 - delayed
Black Pearl acquisition closing. Promised by 2023-12-31.
2023-11-07 - stated
2023-11-07 - delayed
Collateral posting to Oncor Electric Delivery Company 6300000.0 USD. Promised by 2023-12-31.
2023-11-07 - delayed
Black Pearl energization commitment 135.0 MW. Promised by 2026-05-15.
2023-11-07 - delayed
2023-11-07 - stated
2023-11-07 - delayed
Oncor collateral deposit for Black Pearl 6.3 USD. Promised by 2026-05-15.
2025-02-24 - delayed
Black Pearl substation energization 300.0 MW. Promised by 2025-06-30.
2025-02-24 - stated
2025-02-24 - delayed
Black Pearl substation energization. Promised by 2025-06-30.
2025-02-24 - stated
2025-02-24 - delayed
Black Pearl substation energization 300.0 MW. Promised by 2025-06-30.
2025-02-24 - delayed
Black Pearl substation energization 300.0 MW. Promised by 2025-06-30.
2025-02-24 - stated
2025-05-19 - delayed
Mining rigs delivery July 2025. Promised by 2025-07-31.
2025-05-19 - delayed
2025-05-19 - delayed
2025-05-19 - delayed
Black Pearl mining capacity energization 150.0 MW. Promised by 2025-06-30.
2025-05-21 - delayed
2025-05-21 - delayed
Mining rigs arrival for Phase 1. Promised by 2025-07-31.
2025-05-21 - delayed
Black Pearl data center planned capacity 300.0 MW. Promised by 2025-06-30.
2025-05-21 - stated
2025-05-21 - delayed
Black Pearl Phase 1 Energization. Promised by 2025-06-30.
2025-05-21 - delayed
Black Pearl Bitcoin Mining Energization 150.0 MW. Promised by 2025-06-30.
2025-05-21 - delayed
Mining Rigs Delivery to Black Pearl. Promised by 2025-07-31.
2025-05-22 - delayed
2025-05-22 - delayed
Black Pearl Phase 1 energization. Promised by 2025-06-30.
2026-02-02 - stated
Senior secured notes offering 2000000000.0 USD. Promised by 2031-12-31.
2026-02-04 - delayed
Black Pearl Compute senior secured notes offering 2000000000.0 USD. Promised by 2026-02-11.
2026-02-10 - stated
2026-02-10 - stated
2026-02-10 - stated
Senior Secured Notes offering completed 2000000000.0 USD. Promised by 2031-02-15.
2026-02-23 - stated
2026-02-23 - stated
Black Pearl full rent ramp target. Promised by 2027-03-31.
2026-02-23 - stated
Black Pearl full rent ramp. Promised by 2027-03-31.
2026-02-23 - stated
2026-02-23 - stated
Black Pearl full rent ramp. Promised by 2027-03-31.
2026-02-23 - stated
Black Pearl Phase I rent commencement. Promised by 2026-12-31.
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-08-03 - stated