Black Pearl 300 MW data center energization in Q2 2025
Company: Cipher Mining
What the later record shows
Partly delivered · happened June 30, 2025
Black Pearl Phase I (150 of 300 MW) completed construction and energization in Q2 2025. The remaining capacity was redirected to HPC and is being delivered to Amazon in phases starting in 2026.
“Phase I – 150 MW – Construction and energization completed on schedule in Q2 2025”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“to deliver approximately 300 gross MW of turnkey data center capacity at the site”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗
Checked October 30, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of the 300 MW Black Pearl data center is underway, with energization expected in Q2 2025.
Source (primary)
cipher-mining 8-K exhibit (cifr-ex99_1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-30)Live source ↗
Quote: “Construction of 300 MW data center at Black Pearl underway with expected energization in Q2 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (cifr-ex99_1.htm)
Quote: “Construction of 300 MW data center at Black Pearl underway with expected energization in Q2 2025”