Final rent for Black Pearl is expected to commence in March 2027.

Source (primary)

cipher-mining 8-K exhibit (dp240991_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-20)Live source ↗

Quote: “Rent under the final phase is expected to commence in March 2027”

How we checked this

Checked on September 24, 2026. The cited source supports every part of this claim.

The document states rent under the final phase is expected to commence in March 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010326001480/dp240991_ex9901.htm) in full (20,147 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (dp240991_ex9901.htm)

Quote: “Rent under the final phase is expected to commence in March 2027”