Black Pearl substation energization

Company: Cipher Mining - Project: Black Pearl Facility

This claim was marked delayed on September 3, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-02-24
Promised by
2025-06-30
Promised amount
300.0 MW
Current status
delayed

The claim, verbatim

Expect to energize the 300 MW substation in Q2 2025

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We expect to energize the 300 MW substation in the second quarter of 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “We expect to energize the 300 MW substation in the second quarter of 2025”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.