Black Pearl 300 MW facility bitcoin mining energization

Company: Cipher Mining - Project: Black Pearl Facility

Subject kind
facility capacity
Statement date
2025-05-22
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened September 30, 2025

Mining started in June 2025, but the site only reached 150 MW by September 2025, after the June 2025 target.

“We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Plan to energize 150 MW of bitcoin mining capacity in June 2025 at 300 MW data center

Source (primary)

Cipher Mining 424B5 filed 2025-05-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The company overview says Cipher plans to energize 150 MW of bitcoin mining in June 2025 at one 300 MW data center. The claim text does not name the site, and this passage does not name it either.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000119312525125868/d876435d424b5.htm) in full (210,464 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 424B5 filed 2025-05-23

Quote: “including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.