jain.com

Black Pearl Phase I energization 2Q 2025

Company: Cipher Mining - Project: Black Pearl Facility

Subject kind
facility timeline
Statement date
2025-05-05
Promised by
2025-06-30
Current status
verified

What the later record shows

Delivered on time · happened June 30, 2025

Black Pearl Phase I energization was completed on schedule in Q2 2025, and mining began there in June 2025.

“Construction and energization completed on schedule in Q2 2025”
2025-08-06 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-10-08)Live source ↗
“We commenced mining bitcoin at the Black Pearl data center in June 2025”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗

Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Energization of the Black Pearl site is expected in 2Q 2025, with early deployment of about 2.5 EH/s in that quarter.

Source (primary)

cipher-mining 8-K exhibit (exh992ciphermining_busin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “Energization expected in 2Q 2025”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The Black Pearl slide states that energization is expected in 2Q 2025. The growth update says Phase I is on track for early deployment of ~2.5 EH/s in 2Q 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000034/exh992ciphermining_busin.htm) in full (18,992 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (exh992ciphermining_busin.htm)

Quote: “Energization expected in 2Q 2025”

View cached copy (2026-10-16)Live source ↗

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “We commenced mining bitcoin at the Black Pearl data center in June 2025”

View cached copy (2026-08-31)Live source ↗

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “Construction and energization completed on schedule in Q2 2025”

View cached copy (2026-10-08)Live source ↗

Record of changes

October 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 16, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.