Black Pearl Phase I energization

Company: Cipher Mining - Project: Black Pearl Facility

Subject kind
facility timeline
Statement date
2025-08-06
Promised amount
150.0 MW
Event date
2025-06-30
Current status
stated

What the later record shows

Not a promise: a reported event · happened June 30, 2025

The claim, made on 2025-08-06, reports that Phase I construction and energization were already finished in Q2 2025. Later filings confirm Phase I was energized in June 2025.

“In June 2025, we energized and commenced bitcoin mining operations at Phase I of the Black Pearl facility.”
2025-08-06 · Cipher Mining 10-Q filed 2025-08-07 View cached copy (2026-08-31)Live source ↗
“an increase in total bitcoin mined attributable to the Black Pearl Facility coming online at the end of the second quarter of 2025”
2025-11-02 · Cipher Mining 10-Q filed 2025-11-03 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Black Pearl Phase I (150 MW) construction and energization were completed on schedule in Q2 2025, with ~6.9 EH/s currently deployed.

Source (primary)

cipher-mining 8-K exhibit (ciphermining_businessupd.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗

Quote: “Phase I – 150 MW – Construction and energization completed on schedule in Q2 2025 – Current hashrate of ~6.9 EH/s”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The presentation states that Phase I (150 MW) construction and energization were completed on schedule in Q2 2025, with a current hashrate of ~6.9 EH/s.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000079/ciphermining_businessupd.htm) in full (19,841 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “Phase I – 150 MW – Construction and energization completed on schedule in Q2 2025 – Current hashrate of ~6.9 EH/s”

View cached copy (2026-10-08)Live source ↗

Record of changes

October 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.