Black Pearl Phase I 150 MW

Company: Cipher Mining

Subject kind
facility capacity
Statement date
2025-02-24
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened September 30, 2025

The full 150 MW of rigs at Black Pearl was reached by September 2025, after the 2Q 2025 date. In Q2 only about 6.9 EH/s was deployed. The Q3 hashrate increase is attributed to completion of Phase I 150 MW.

“End of Period Self-Mining Hashrate ~23.6 EH/s ~16.8 EH/s ~40% Increase Driven by completion of Black Pearl Phase I 150 MW”
2025-11-02 · cipher-mining 8-K exhibit (ciphermining_businessupd.htm) View cached copy (2026-09-27)Live source ↗
“We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗

Checked October 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Black Pearl Phase I is planned as 150 MW of air-cooled mining rigs that can generate about 9.5+ EH/s.

Source (primary)

cipher-mining 8-K exhibit (exh992revduploadtoworkiv.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗

Quote: “Phase I envisions 150 MW of air-cooled rigs that can generate ~9.5+ EH/s(1)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (exh992revduploadtoworkiv.htm)

Quote: “Phase I envisions 150 MW of air-cooled rigs that can generate ~9.5+ EH/s(1)”

View cached copy (2026-10-19)Live source ↗

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”

View cached copy (2026-08-31)Live source ↗

confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)

Quote: “End of Period Self-Mining Hashrate ~23.6 EH/s ~16.8 EH/s ~40% Increase Driven by completion of Black Pearl Phase I 150 MW”

View cached copy (2026-09-27)Live source ↗

Record of changes

October 19, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 19, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.