Black Pearl ERCOT power approval
Company: Cipher Mining - Project: Black Pearl Facility
The claim, verbatim
Obtained conditional ERCOT approval for up to 300 MW energy consumption at Black Pearl interconnection point
Source (primary)
Cipher Mining 8-K filed 2023-11-08 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “an approval from the Electric Reliability Council of Texas ("ERCOT") conditionally approving up to 300 MW of energy consumption at the interconnection point of the Leased Property”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Cipher Mining 8-K filed 2023-11-08
Quote: “an approval from the Electric Reliability Council of Texas ("ERCOT") conditionally approving up to 300 MW of energy consumption at the interconnection point of the Leased Property”