Black Pearl gross capacity
Company: Cipher Mining - Project: Black Pearl Facility
The claim, verbatim
Black Pearl will have 300 MW of gross data center capacity.
Source (primary)
cipher-mining 8-K exhibit (dp240991_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-20)Live source ↗
Quote: “300 MW Gross Capacity”
How we checked this
Checked on September 24, 2026. The cited source supports every part of this claim.
The document repeatedly describes Black Pearl as a 300 gross MW facility.
Confirmed in the source:
- Black Pearl has 300 MW of gross capacity
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010326001480/dp240991_ex9901.htm) in full (20,147 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (dp240991_ex9901.htm)
Quote: “300 MW Gross Capacity”