Cipher announced a partnership to build 300 MW gross data center capacity at Black Pearl, Wink, TX, leased to Amazon Data Services, Inc. for at least 15 years.

Source (primary)

cipher-mining 8-K exhibit (dp240991_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-20)Live source ↗

Quote: “On Nov. 3, 2025, Cipher announced a new partnership to build 300 MW of gross data center capacity which will be leased to Amazon Data Services, Inc. for at least 15 years”

How we checked this

Checked on September 24, 2026. The cited source supports every part of this claim.

The document states Cipher announced a partnership to build 300 MW of gross capacity at Black Pearl in Wink, Texas, leased to Amazon Data Services for at least 15 years.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010326001480/dp240991_ex9901.htm) in full (20,147 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (dp240991_ex9901.htm)

Quote: “On Nov. 3, 2025, Cipher announced a new partnership to build 300 MW of gross data center capacity which will be leased to Amazon Data Services, Inc. for at least 15 years”