jain.com

Black Pearl Bitcoin Mining Energization

Company: Cipher Mining - Project: Black Pearl Facility

Subject kind
facility timeline
Statement date
2025-05-21
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened September 30, 2025

Black Pearl reached 150 MW of mining capacity by September 2025, not the June 2025 target.

“We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company plans to energize 150 MW of bitcoin mining at Black Pearl data center in June 2025

Source (primary)

Cipher Mining 424B5 filed 2025-05-22 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025”

How we checked this

Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.

The filing mentions a planned 150 MW June 2025 energization at an unnamed 300 MW site. It separately says Phase 1 of Black Pearl is to be energized in June 2025. It never explicitly states that the 150 MW site is Black Pearl.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000119312525124285/d920705d424b5.htm) in full (435,499 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 424B5 filed 2025-05-22

Quote: “one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in June 2025”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.