Black Pearl mining capacity energization

Company: Cipher Mining - Project: Black Pearl Facility

Subject kind
facility timeline
Statement date
2025-05-19
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered late · happened September 30, 2025

150 MW was reached by September 2025. That is within the claim's own 'in 2025' wording but after the recorded June 30, 2025 promised date.

“We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”
2026-02-23 · Cipher Mining 10-K filed 2026-02-24 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The company plans to energize 150 MW of bitcoin mining at a 300 MW data center in Texas in 2025

Source (primary)

Cipher Mining 424B5 filed 2025-05-20 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in 2025”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus describes a pipeline of about 2.8 GW across seven additional Texas sites, including one 300 MW data center where the company plans to energize 150 MW of bitcoin mining in 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000119312525123231/d920705d424b5.htm) in full (436,841 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 424B5 filed 2025-05-20

Quote: “including one 300 MW data center at which we plan to energize 150 MW of bitcoin mining in 2025”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “We commenced mining bitcoin at the Black Pearl data center in June 2025 and ramped up to 150 MW of capacity by September 2025.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.