Cottonwood
Project of Core Scientific
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 300 MW | 2026-03-01 | Pecos, Texas facility |
| Contracted a customer is on the hook | -- | ||
| Under construction | 100 MW | 2026-09-01 | Pecos TX 100 MW expansion underway |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 1,500 MW | 2026-04-26 | Pecos campus gross power capacity target |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-07-27
Advanced Micro Devices - tenant ยท 15-year term source
Claims about this project
2026-03-01 - stated
Pecos, Texas facility 300.0 MW.
2026-04-26 - stated
2026-04-26 - stated
2026-07-28 - stated
Pecos Texas campus deliveries. Promised by 2027-06-30.
2026-09-01 - stated
Pecos TX 100 MW expansion underway 100.0 MW.
2026-09-01 - stated
Cottonwood COT1 lease term expiration. Promised by 2031-11-30.
2026-09-01 - stated
Pecos billable power capacity 200.0 MW.
2026-09-01 - stated
Cottonwood COT2 operational capacity 21.0 MW.
2026-09-01 - stated
Cottonwood COT1 operational capacity 50.0 MW.
2026-09-01 - stated
Pecos TX Cottonwood facility capacity 250.0 MW.
2026-09-01 - stated
Cottonwood COT2 99-year lease term. Promised by 2122-12-31.
2026-09-01 - stated
Pecos TX site delivery. Promised by 2027-06-30.