jain.com

21 MW expansion at Pecos

Company: Core Scientific

Subject kind
facility capacity
Statement date
2024-05-07
Promised amount
21.0 MW
Current status
stated

The claim, verbatim

Core Scientific expanded operational infrastructure at its Pecos, Texas site by 21 MW.

Source (primary)

core-scientific 8-K exhibit (q12024corescientificinc-ea.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗

Quote: “Expanded operational infrastructure by 21 MW at Pecos, Texas site”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (q12024corescientificinc-ea.htm)

Quote: “Expanded operational infrastructure by 21 MW at Pecos, Texas site”

View cached copy (2026-11-06)Live source ↗