Cottonwood build-out to 250MW

Company: Core Scientific

Subject kind
facility capacity
Statement date
2023-06-20
Promised by
2025-12-31
Promised amount
250.0 MW
Current status
stated

The claim, verbatim

Core anticipates building the Cottonwood facility to its full capacity of 250MW by year-end 2025.

Source (primary)

core-scientific 8-K exhibit (d398991dex993.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-23)Live source ↗

Quote: “Core anticipates building Cottonwood to its full capacity by year-end 2025 (i.e., 250MW)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (d398991dex993.htm)

Quote: “Core anticipates building Cottonwood to its full capacity by year-end 2025 (i.e., 250MW)”

View cached copy (2026-11-23)Live source ↗