jain.com

Cottonwood COT1 operational capacity

Company: Core Scientific - Project: Cottonwood

Subject kind
facility capacity
Statement date
2026-09-01
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

Cottonwood COT1 has 1 operational building with 50 MW of energized capacity

Source (primary)

Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗

Quote: “COT1 - (1) Operational Building totaling 50MW of energized capacity (~15k miners)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Second Quarter Fiscal Year 2024 Earnings Presentation

Quote: “COT1 - (1) Operational Building totaling 50MW of energized capacity (~15k miners)”

View cached copy (2026-09-01)Live source ↗