jain.com

Pecos TX 100 MW build-out project begun

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-07-04
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

Core Scientific began a project to complete 100 MW of partially built infrastructure at its Pecos, Texas data center to house bitcoin miners relocated from sites being modified for HPC hosting; no completion date given.

Source (primary)

core-scientific 8-K exhibit (finalcorzjune24updaterelea.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗

Quote: “The Company also began a project to complete 100 MW of partially built infrastructure at its Pecos, Texas data center. These expansions will house bitcoin miners relocated from sites scheduled for modification to support HPC hosting.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (finalcorzjune24updaterelea.htm)

Quote: “The Company also began a project to complete 100 MW of partially built infrastructure at its Pecos, Texas data center. These expansions will house bitcoin miners relocated from sites scheduled for modification to support HPC hosting.”