First data hall construction milestone at Pecos

Company: Core Scientific - Project: Cottonwood

Subject kind
facility timeline
Statement date
2026-04-26
Current status
stated

The claim, verbatim

The first data hall at Pecos has reached a critical construction milestone with interior foundational footings set and precast concrete walls arriving on site

Source (primary)

core-scientific 8-K exhibit (exhibit991-pecosexpansio.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗

Quote: “The first data hall has reached a critical construction milestone, with its interior foundational footings set, marking the start of the next phase of construction. Precast concrete walls are arriving on site as the project moves toward vertical construction”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (exhibit991-pecosexpansio.htm)

Quote: “The first data hall has reached a critical construction milestone, with its interior foundational footings set, marking the start of the next phase of construction. Precast concrete walls are arriving on site as the project moves toward vertical construction”

View cached copy (2026-09-09)Live source ↗