First data hall construction milestone at Pecos
Company: Core Scientific - Project: Cottonwood
The claim, verbatim
The first data hall at Pecos has reached a critical construction milestone with interior foundational footings set and precast concrete walls arriving on site
Source (primary)
core-scientific 8-K exhibit (exhibit991-pecosexpansio.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-09)Live source ↗
Quote: “The first data hall has reached a critical construction milestone, with its interior foundational footings set, marking the start of the next phase of construction. Precast concrete walls are arriving on site as the project moves toward vertical construction”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
Both assertions appear verbatim in the document.
Confirmed in the source:
- The first data hall at Pecos reached a critical construction milestone with interior foundational footings set
- Precast concrete walls are arriving on site
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828026027645/exhibit991-pecosexpansio.htm) in full (6,375 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms core-scientific 8-K exhibit (exhibit991-pecosexpansio.htm)
Quote: “The first data hall has reached a critical construction milestone, with its interior foundational footings set, marking the start of the next phase of construction. Precast concrete walls are arriving on site as the project moves toward vertical construction”