jain.com

Pecos, TX 100 MW expansion completed

Company: Core Scientific - Project: Cottonwood

Subject kind
facility capacity
Statement date
2024-12-03
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

The company completed a 100 MW expansion at its Pecos, TX bitcoin mining data center.

Source (primary)

December 2024 Convertible Note Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗

Quote: “Completed 100 MW expansion at Pecos, TX bitcoin mining data center”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The presentation states the completed 100 MW Pecos expansion in both the accomplishments timeline and the 2024 snapshot.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11131/pdf/Core_Scientific_December_2024_Company_Presentation.pdf) in full (23,998 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms December 2024 Convertible Note Presentation

Quote: “Completed 100 MW expansion at Pecos, TX bitcoin mining data center”

View cached copy (2026-10-16)Live source ↗