Pecos existing 300 MW Base Load capacity approved
Company: Core Scientific - Project: Cottonwood
The claim, verbatim
Existing 300 MW at Pecos approved in Batch Zero as Base Load Pathway (b)
Source (primary)
Core Scientific wins conditional ERCOT power approvals for Texas data centers - TradingView (-, news_article)
View cached copy (2026-09-11)Live source ↗Archive.org ↗
Quote: “Pecos: Existing 300 MW approved in Batch Zero as Base Load Pathway (b)”
How we checked this
Checked on September 20, 2026. The cited source supports every part of this claim.
The document states that Pecos's existing 300 MW was approved in Batch Zero as Base Load Pathway (b).
Confirmed in the source:
- Core Scientific's Pecos facility has an existing 300 MW approved in Batch Zero as Base Load Pathway (b)
What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/tradingview:b55357bd92728:0-core-scientific-wins-conditional-ercot-power-approvals-for-texas-data-centers/) in full (3,369 characters, retrieved September 11, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Core Scientific wins conditional ERCOT power approvals for Texas data centers - TradingView
Quote: “Pecos: Existing 300 MW approved in Batch Zero as Base Load Pathway (b)”