Vineland
Project of Nebius
Where it stands
Nebius's build-to-suit Vineland, NJ campus, developed by DataOne, is a phased project of about 300 MW, with a possible expansion to 350 MW. Its April 2026 20-F says Nebius 'is providing' Microsoft GPU capacity there in tranches being deployed through 2025–2026, so some capacity appears to be in service, though no operating MW figure is disclosed. Phase 1 is reported as still under construction, Phase 2 won planning approval in August 2026, power is shifting to Bloom fuel cells, and management says it expects no significant impact on timing.
300 MW planned
| Phase | MW | Status | Date | Source |
|---|---|---|---|---|
| Phase 1 | under construction | 2026-08-18 | Phase 1 is already under construction, and Phase 2 will add 600,000 square feet to the project. 2026-08-18 View cached copy (2026-08-31)Live source ↗ | |
| Phase 2 | planned | 2026-08-18 | The Vineland Planning Board voted to approve Phase 2 of the data center already under construction in the South Jersey town on Monday night 2026-08-18 View cached copy (2026-08-31)Live source ↗ |
Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: September 7, 2026).
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 100 MW | 2025-08-06 | New Jersey additional 100 MW in 2026 |
| Under construction | 100 MW | 2025-08-06 | New Jersey 100 MW available in 2025 |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 300 MW | 2026-08-18 | Vineland data center project capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
Site intelligence
How we located this site
- Initial geocode 2026-09-05
Vineland, New Jersey, NJ → town/county centre, 4 km box -- not the site - Nearest substation (earlier method) 2026-09-05
re-centred on the nearest high-voltage substation (superseded method) - Starting point (the project's stated locality) 2026-10-19
Vineland, New Jersey → 39.48694, -75.04310 (locality) - No site-level evidence yet 2026-10-19
no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site - OpenStreetMap features nearby 2026-10-19
0 named match(es)
Satellite imagery on this page is drawn from the Google Earth satellite basemap. Each image is dated, labelled by source and pixel resolution, and downloadable at its native size; cloudy dates are kept and marked rather than hidden. New scenes are pulled daily as each provider publishes them.




