Vineland
Project of Nebius
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | -- | ||
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 300 MW | 2026-08-18 | Vineland Data Center Capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2025-09-07
Microsoft Corporation - tenant ยท 5-year term source
Claims about this project
2025-09-07 - stated
2025-09-07 - stated
2025-09-07 - stated
Optional additional services value 19.4 billion USD.
2025-09-07 - stated
2025-09-09 - delayed
Vineland, New Jersey data center initial capacity availability. Promised by 2025-12-31.
2025-09-09 - stated
2025-09-11 - stated
Microsoft GPU infrastructure services contract 17400000000.0 USD.
2025-09-11 - stated
Microsoft optional additional services 19400000000.0 USD.
2025-09-11 - stated
2025-11-11 - stated
Microsoft GPU infrastructure agreement 17.4 USD billion.
2025-11-11 - stated
Microsoft GPU cluster deployment. Promised by 2026-12-31.
2026-08-18 - stated
Vineland Data Center Capacity 300.0 MW.