Microsoft GPU cluster deployment

Company: Nebius - Project: Vineland

Subject kind
facility timeline
Statement date
2025-11-11
Promised by
2026-12-31
Current status
stated

The claim, verbatim

Will deploy GPU services to Microsoft in several tranches during 2025 and 2026 at Vineland, New Jersey facility

Source (primary)

Nebius 424B5 filed 2025-11-12 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We will deploy the GPU services in several tranches during 2025 and 2026”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The document states the several-tranche 2025-2026 deployment and, in the same paragraph, that the Microsoft capacity is at the Vineland, New Jersey data center.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1513845/000110465925110025/tm2530771-1_424b5.htm) in full (236,056 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Nebius 424B5 filed 2025-11-12

Quote: “We will deploy the GPU services in several tranches during 2025 and 2026”

View cached copy (2026-08-31)Live source ↗