jain.com

Bloom contract installed capacity ~328 MW

Company: Nebius

Subject kind
facility capacity
Statement date
2026-10-23
Promised amount
328.0 MW
Current status
stated

The claim, verbatim

Per a Nebius filing, the Bloom contract covers about 328 MW of installed fuel-cell capacity.

Source (primary)

Bloom Energy says first power block is ready at Nebius’s 300 MW New Jersey data center - Yahoo Finance (-, news_article)
View cached copy (2026-10-28)Live source ↗Archive.org ↗

Quote: “about 328 MW of installed capacity, according to a Nebius filing”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Bloom Energy says first power block is ready at Nebius’s 300 MW New Jersey data center - Yahoo Finance

Quote: “about 328 MW of installed capacity, according to a Nebius filing”

View cached copy (2026-10-28)Live source ↗Archive.org ↗