New Jersey 100 MW available in 2025
Company: Nebius - Project: Vineland
What the later record shows
Outcome not yet confirmed
No passage reports how many megawatts at New Jersey were available in 2025. In August 2026 management described Vineland as part of its 2026 connected-power capacity, which does not confirm or rule out 100 MW in 2025.
“No, the Vineland is the part of 2026 capacity and connected power.”
2026-08-19 · Nebius (NBIS) Q2 2026 Earnings Call Transcript - The Motley Fool View cached copy (2026-08-31)Live source ↗Archive.org ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Of 200 MW contracted power in active construction in New Jersey, 100 MW will be made available in 2025.
Source (primary)
nebius 8-K exhibit (tm2522866d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗
Quote: “We now have 200 MW of contracted power that is in active construction in New Jersey, of which 100 MW will be made available this year”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The letter states that 100 MW of the 200 MW under construction in New Jersey will be available this year.
Confirmed in the source:
- Nebius has 200 MW of contracted power in active construction in New Jersey
- 100 MW of that power will be made available in 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925075028/tm2522866d1_ex99-2.htm) in full (32,613 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms nebius 8-K exhibit (tm2522866d1_ex99-2.htm)
Quote: “We now have 200 MW of contracted power that is in active construction in New Jersey, of which 100 MW will be made available this year”