Vineland, NJ data center to begin delivering Microsoft capacity in 2025

Company: Nebius - Project: Vineland

Subject kind
facility timeline
Statement date
2025-09-07
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered; the record does not say when

As of November 12, 2025, delivery to Microsoft was still expected to begin later in the year. By the April 2026 20-F, Nebius said it was providing Microsoft capacity at Vineland. No passage confirms that delivery started in 2025.

“the Group expects to deliver dedicated capacity to Microsoft from its new data center in Vineland, New Jersey starting later this year”
2025-11-12 · nebius 8-K exhibit (tm2531034d1_ex99-1.htm) View cached copy (2026-09-26)Live source ↗
“pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”
2026-04-29 · Nebius 20-F filed 2026-04-30 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Nebius will deliver dedicated capacity to Microsoft from its new Vineland, New Jersey data center starting later in 2025.

Source (primary)

nebius 8-K exhibit (tm2525580d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-04)Live source ↗

Quote: “Nebius will deliver dedicated capacity to Microsoft from its new data center in Vineland, New Jersey starting later this year”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The September 8, 2025 press release states that Nebius will deliver dedicated capacity to Microsoft from its new Vineland, New Jersey data center starting later that year, which establishes every part of the claim.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925088312/tm2525580d1_ex99-1.htm) in full (6,396 characters, retrieved October 4, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2525580d1_ex99-1.htm)

Quote: “Nebius will deliver dedicated capacity to Microsoft from its new data center in Vineland, New Jersey starting later this year”

View cached copy (2026-10-04)Live source ↗

confirms Nebius 20-F filed 2026-04-30

Quote: “pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”

View cached copy (2026-08-31)Live source ↗

confirms nebius 8-K exhibit (tm2531034d1_ex99-1.htm)

Quote: “the Group expects to deliver dedicated capacity to Microsoft from its new data center in Vineland, New Jersey starting later this year”

View cached copy (2026-09-26)Live source ↗

Record of changes

October 4, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 5, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.