Vineland site power delay
Company: Nebius - Project: Vineland
The claim, verbatim
The Vineland site delay stemmed primarily from power availability after DataOne wound down temporary generation early; Bloom generation is live but must ramp up.
Source (primary)
Nebius Group Q3 Earnings Call Highlights - Yahoo Finance (-, news_article)
View cached copy (2026-11-13)Live source ↗
Quote: “At the Vineland site, Chief Infrastructure and Product Officer Andrey Korolenko said the delay stemmed primarily from power availability.”
How we checked this
Checked on November 15, 2026. The cited source supports every part of this claim.
The article attributes each element to Andrey Korolenko: the power cause, the faster-than-expected DataOne wind-down, and Bloom being live but still ramping.
Confirmed in the source:
- Korolenko said the Vineland site delay stemmed primarily from power availability
- DataOne decided to wind down temporary generation faster than expected while Bloom generation was being deployed
- Bloom generation is live at the site but needs to ramp up
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/nebius-group-q3-earnings-call-191451371.html) in full (15,234 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Nebius Group Q3 Earnings Call Highlights - Yahoo Finance
Quote: “At the Vineland site, Chief Infrastructure and Product Officer Andrey Korolenko said the delay stemmed primarily from power availability.”