Vineland, NJ facility opening end of summer 2025

Company: Nebius - Project: Vineland

Subject kind
facility timeline
Statement date
2025-08-06
Promised by
2025-09-22
Current status
verified

What the later record shows

Delivered; the record does not say when

The April 2026 20-F says Nebius is providing GPU capacity from the Vineland data center, so the facility is operating. No passage gives an opening date. A November 2025 filing still described Vineland only as under construction, which suggests the end-of-summer 2025 opening may have been missed.

“began construction of a build-to-suit facility in Vineland, New Jersey. In addition, we opened our first GPU clusters in the UK and Israel in late 2025”
2025-11-11 · Nebius 424B5 filed 2025-11-12 View cached copy (2026-08-31)Live source ↗
“pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”
2026-04-29 · Nebius 20-F filed 2026-04-30 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Nebius's new New Jersey facility is on track to open by end of summer 2025, with instances offered from it in fall 2025.

Source (primary)

nebius 8-K exhibit (tm2522866d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗

Quote: “Our new facility in Vinefield, New Jersey is on track to open by the end of the summer and we plan to offer instances from this facility this fall.”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The letter states the New Jersey facility's end-of-summer opening and fall availability of instances. It spells the town 'Vinefield.'

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465925075028/tm2522866d1_ex99-2.htm) in full (32,613 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2522866d1_ex99-2.htm)

Quote: “Our new facility in Vinefield, New Jersey is on track to open by the end of the summer and we plan to offer instances from this facility this fall.”

View cached copy (2026-10-08)Live source ↗

confirms Nebius 424B5 filed 2025-11-12

Quote: “began construction of a build-to-suit facility in Vineland, New Jersey. In addition, we opened our first GPU clusters in the UK and Israel in late 2025”

View cached copy (2026-08-31)Live source ↗

confirms Nebius 20-F filed 2026-04-30

Quote: “pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.