jain.com

Vineland, New Jersey data center initial capacity availability

Company: Nebius - Project: Vineland

Subject kind
facility timeline
Statement date
2025-09-09
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered; the record does not say when

By April 2026 the Vineland facility was serving Microsoft, with tranches deployed during 2025 and 2026, so initial capacity exists. No passage says whether it became available before the end of 2025.

“pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”
2026-04-29 · Nebius 20-F filed 2026-04-30 View cached copy (2026-08-31)Live source ↗
“The Microsoft GPU Services are being deployed in nine tranches during 2025 and 2026.”
2026-04-29 · Nebius 20-F filed 2026-04-30 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Initial capacity at Vineland, New Jersey build-to-suit facility expected to be available in second half of 2025.

Source (primary)

Nebius 424B5 filed 2025-09-10 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “In early 2025, we commissioned our first US-based co-location site in Kansas City, Missouri and began construction of a build-to-suit facility in Vineland, New Jersey. The New Jersey site is a phased development with initial capacity expected to be available in the second half of 2025.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus supplement states that Nebius began building a build-to-suit facility in Vineland, New Jersey, and that initial capacity at this phased site was expected to be available in the second half of 2025. This matches the claim; the timing is stated as an expectation, not a completed event.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1513845/000110465925088885/tm2525503-3_424b5.htm) in full (287,346 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Nebius 424B5 filed 2025-09-10

Quote: “In early 2025, we commissioned our first US-based co-location site in Kansas City, Missouri and began construction of a build-to-suit facility in Vineland, New Jersey. The New Jersey site is a phased development with initial capacity expected to be available in the second half of 2025.”

View cached copy (2026-08-31)Live source ↗

confirms Nebius 20-F filed 2026-04-30

Quote: “pursuant to which we are providing Microsoft access to dedicated GPU infrastructure capacity in clusters at our new data center in Vineland, New Jersey over a five-year term”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.