Delayed third-party capacity shifted to Q2 2027
Company: Nebius - Project: Vineland
The claim, verbatim
Some delayed third-party colocation capacity, including New Jersey, shifted into Q2 2027; none was canceled.
Source (primary)
Nebius Group Q3 Earnings Call Highlights - Yahoo Finance (-, news_article)
View cached copy (2026-11-13)Live source ↗
Quote: “Alonso said some third-party capacity had shifted into the second quarter of 2027.”
How we checked this
Checked on November 15, 2026. The cited source supports part of this claim, but not all of it.
The article says New Jersey capacity slipped into 2027 and, separately, that some third-party capacity moved to Q2 2027. It does not tie the New Jersey capacity to Q2 specifically.
Confirmed in the source:
- Some colocation sites, including New Jersey, were behind schedule, shifting some planned revenue into 2027
- CFO Dado Alonso said some third-party capacity had shifted into the second quarter of 2027
- None of the affected capacity was canceled, according to CEO Arkady Volozh
We could not confirm this from the cited source:
- The delayed New Jersey capacity specifically shifted into the second quarter of 2027, as opposed to some other point in 2027
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/nebius-group-q3-earnings-call-191451371.html) in full (15,234 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Nebius Group Q3 Earnings Call Highlights - Yahoo Finance
Quote: “Alonso said some third-party capacity had shifted into the second quarter of 2027.”
confirms Nebius pares back 2026 revenue forecast on capacity delays, shares slump - marketscreener.com
Quote: “some third-party capacity expected to come online this year had been pushed back to the first half of 2027, though the contracts underpinning that capacity remained in place”