Nebius New Jersey site: 140 MW may slip into 2027

Company: Nebius

Subject kind
facility timeline
Statement date
2026-11-05
Promised amount
140.0 MW
Current status
stated

The claim, verbatim

According to Aterio data analyst Daud Shiraz, roughly 140 MW of planned capacity at the New Jersey project developed by DataOne for Nebius could slip into 2027 because of generator permitting difficulties and further approval delays after a switch to fuel cells.

Source (primary)

Microsoft's $5B AI Capex Gap: Satellite Images Point to Delays at IREN, Nebius Sites - BigGo Finance (-, news_article)
View cached copy (2026-11-05)Live source ↗

Quote: “roughly 140 megawatts of that project's planned capacity could slip into 2027 after difficulties securing permits for its original generators and further approval delays following a switch to fuel cells”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Microsoft's $5B AI Capex Gap: Satellite Images Point to Delays at IREN, Nebius Sites - BigGo Finance

Quote: “roughly 140 megawatts of that project's planned capacity could slip into 2027 after difficulties securing permits for its original generators and further approval delays following a switch to fuel cells”

View cached copy (2026-11-05)Live source ↗