New Jersey remaining tranches delayed to 2Q27

Company: Nebius - Project: Vineland

Subject kind
facility timeline
Statement date
2026-11-11
Promised by
2027-06-30
Current status
stated

The claim, verbatim

Remaining New Jersey tranches for Microsoft are now scheduled for Q2 2027.

Source (primary)

nebius 8-K exhibit (tm2629571d1_ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-13)Live source ↗

Quote: “with the remaining tranches now scheduled for 2Q27”

How we checked this

Checked on November 15, 2026. The cited source supports every part of this claim.

The letter says the remaining New Jersey tranches of Microsoft-contracted capacity are now scheduled for 2Q27. It also says their delivery dates shifted into the first half of 2027.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-2.htm) in full (50,173 characters, retrieved November 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms nebius 8-K exhibit (tm2629571d1_ex99-2.htm)

Quote: “with the remaining tranches now scheduled for 2Q27”