What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 207 MW | 2026-08-03 | Odessa Facility bitcoin mining capacity |
| Contracted a customer is on the hook | -- | ||
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | -- |
Claims about this project
2025-02-24 - stated
Odessa Facility capacity 11.3 EH/s.
2025-02-24 - stated
2025-02-24 - stated
Odessa Facility capacity 207.0 MW.
2025-02-24 - stated
2025-02-24 - stated
Odessa power supply agreement through July 2027. Promised by 2027-07-31.
2025-02-24 - stated
2025-02-24 - stated
Luminant take-or-pay obligation 66.7 percent.
2025-02-24 - stated
2025-05-19 - stated
Odessa Facility bitcoin mining capacity 207.0 MW.
2025-05-19 - stated
Odessa Facility hashrate capacity 11.3 EH/s.
2025-05-19 - stated
Odessa Facility hashrate capacity 11.3 EH/s.
2025-05-21 - stated
Odessa Facility Hashrate 11.3 EH/s.
2025-05-21 - stated
Odessa Facility hashrate capacity 11.3 EH/s.
2025-05-21 - stated
2025-05-21 - stated
Odessa Facility Capacity 207.0 MW.
2026-02-23 - stated
2026-02-23 - stated
Odessa bitcoin mining facility 207.0 MW.
2026-02-23 - stated
2026-02-23 - stated
Luminant power purchase agreement. Promised by 2027-07-31.
2026-02-23 - stated
Odessa power cost 2.8 c/kWh.
2026-02-23 - stated
Odessa bitcoin mining facility capacity 207.0 MW.
2026-02-23 - stated
Odessa bitcoin mining facility capacity 207.0 MW.
2026-02-23 - stated
Bitcoin mining operations capacity 207.0 MW.
2026-08-03 - stated
Odessa Facility bitcoin mining capacity 207.0 MW.