jain.com

Odessa Facility bitcoin mining capacity

Company: Cipher Mining - Project: Odessa Facility

Subject kind
facility capacity
Statement date
2026-08-03
Promised amount
207.0 MW
Current status
stated

The claim, verbatim

Cipher operates one wholly owned 207 MW bitcoin mining data center in Odessa, Texas with fixed-price power from a power purchase agreement

Source (primary)

Cipher Mining 10-Q filed 2026-08-04 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “The Company operates one wholly owned bitcoin mining data center, a 207 MW site located in Odessa, Texas that draws fixed priced power from a power purchase agreement with its electricity provider (the "Odessa Facility").”

How we checked this

Checked on September 2, 2026. The cited source supports every part of this claim.

Every element of the claim appears in Note 1 of the filing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000041/cifr-20260630.htm) in full (220,815 characters, retrieved August 30, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-Q filed 2026-08-04

Quote: “The Company operates one wholly owned bitcoin mining data center, a 207 MW site located in Odessa, Texas that draws fixed priced power from a power purchase agreement with its electricity provider (the "Odessa Facility").”

View cached copy (2026-08-30)Live source ↗