jain.com

Planned electricity delivery ramp at Odessa facility

Company: Cipher Mining - Project: Odessa Facility

Subject kind
facility capacity
Statement date
2022-09-01
Promised by
2023-02-28
Promised amount
207.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

By March 2023 the company described the full 207MW capacity and was selling unconsumed power into ERCOT. Later filings call Odessa a 207 MW facility whose buildout was completed in September 2023. No passage says when deliveries reached 207 MW relative to February 2023.

“we plan either to sell the excess power that we don't consume for bitcoin mining and operating the data center into the ERCOT market”
2023-03-13 · Cipher Mining 10-K filed 2023-03-14 View cached copy (2026-09-13)Live source ↗
“We began bitcoin mining operations on this site in November 2022 and completed the buildout of the site in September 2023.”
2024-03-04 · Cipher Mining 10-K filed 2024-03-05 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Cipher will ramp up electricity delivery at the Odessa, Texas facility to a planned maximum of 207 MW by February 2023, with intermediate monthly milestones from July 2022 through February 2023

Source (primary)

Cipher Mining 424B3 filed 2022-09-02 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The 'Ramp Up schedule' shall be as follows: Date Quantity July-22 2-MW August-22 35-MW September-22 2-MW October-22 35-MW November-22 70-MW December-22 105-MW January-2023 177-MW February-2023 207-MW”

How we checked this

Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.

The document does contain the monthly schedule ending at 207 MW in February 2023. It does not call 207 MW a maximum, and the schedule is not a continuous ramp-up.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000119312522237762/d384795d424b3.htm) in full (18,901 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 424B3 filed 2022-09-02

Quote: “The 'Ramp Up schedule' shall be as follows: Date Quantity July-22 2-MW August-22 35-MW September-22 2-MW October-22 35-MW November-22 70-MW December-22 105-MW January-2023 177-MW February-2023 207-MW”

View cached copy (2026-09-13)Live source ↗

confirms Cipher Mining 10-K filed 2024-03-05

Quote: “We began bitcoin mining operations on this site in November 2022 and completed the buildout of the site in September 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Cipher Mining 10-K filed 2023-03-14

Quote: “we plan either to sell the excess power that we don't consume for bitcoin mining and operating the data center into the ERCOT market”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.