Odessa Q1 2023 capacity target
Company: Cipher Mining - Project: Odessa Facility
What the later record shows
Delivered; the record does not say when
Later filings show 61,024 miners at Odessa by June 30, 2023 and about 6.4 EH/s by February 2024, both above target. The status at the end of Q1 2023 is not disclosed.
“As of June 30, 2023 , the Company had 61,024 miners located at the Odessa Facility”
2023-08-07 · Cipher Mining 10-Q filed 2023-08-08 View cached copy (2026-09-13)Live source ↗
“As of February 29, 2024, the Odessa Facility is capable of producing approximately 6.4 EH/s through the operation of approximately 60,000 miners.”
2024-03-04 · Cipher Mining 10-K filed 2024-03-05 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
By end of Q1 2023, Odessa will operate approximately 47,000 miners capable of generating 4.7 EH/s
Source (primary)
Cipher Mining 10-K filed 2023-03-14 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “By the end of the first quarter 2023, we anticipate operating approximately 47,000 miners, capable of generating approximately 4.7 EH/s”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The figures match the 10-K, but the filing frames them as what the company anticipated, not as a certainty.
Confirmed in the source:
- Cipher anticipated operating approximately 47,000 miners at Odessa by the end of Q1 2023
- Those miners were anticipated to be capable of approximately 4.7 EH/s
We could not confirm this from the cited source:
- That Odessa definitely will operate 47,000 miners at 4.7 EH/s by end of Q1 2023 (the filing presents this only as an anticipation, not a commitment)
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000095017023007793/cifr-20221231.htm) in full (564,500 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Cipher Mining 10-K filed 2023-03-14
Quote: “By the end of the first quarter 2023, we anticipate operating approximately 47,000 miners, capable of generating approximately 4.7 EH/s”
confirms Cipher Mining 10-K filed 2024-03-05
Quote: “As of February 29, 2024, the Odessa Facility is capable of producing approximately 6.4 EH/s through the operation of approximately 60,000 miners.”
confirms Cipher Mining 10-Q filed 2023-08-08
Quote: “As of June 30, 2023 , the Company had 61,024 miners located at the Odessa Facility”