jain.com

Odessa bitcoin mining facility capacity

Company: Cipher Mining - Project: Odessa Facility

Subject kind
facility capacity
Statement date
2026-02-23
Promised amount
207.0 MW
Current status
stated

The claim, verbatim

Odessa data center is a wholly-owned 207 MW facility in Odessa, Texas

Source (primary)

Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Our Odessa data center (the "Odessa Facility") is our wholly-owned 207 MW facility located in Odessa, Texas.”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The Bitcoin Mining Operations section describes the Odessa Facility in exactly these terms.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) in full (477,779 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “Our Odessa data center (the "Odessa Facility") is our wholly-owned 207 MW facility located in Odessa, Texas.”

View cached copy (2026-08-31)Live source ↗