Odessa Facility Capacity
Company: Cipher Mining - Project: Odessa Facility
The claim, verbatim
Company currently operates one wholly-owned 207 MW bitcoin mining data center (Odessa Facility)
Source (primary)
Cipher Mining 424B5 filed 2025-05-22 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We currently operate one wholly-owned 207 MW bitcoin mining data center”
How we checked this
Additional evidence
confirms Cipher Mining 424B5 filed 2025-05-22
Quote: “We currently operate one wholly-owned 207 MW bitcoin mining data center”