jain.com

Luminant power cost

Company: Cipher Mining - Project: Odessa Facility

Subject kind
financing
Statement date
2025-02-24
Promised by
2027-07-31
Promised amount
2.7 c/kWh
Current status
stated

The claim, verbatim

Company has access to electricity at Odessa Facility at cost of approximately 2.7 cents per kilowatt-hour through at least July 2027

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “pursuant to which we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998925000005/cifr-20241231.htm) in full (492,885 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “pursuant to which we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh”

View cached copy (2026-08-31)Live source ↗