Luminant power cost

Company: Cipher Mining - Project: Odessa Facility

Subject kind
financing
Statement date
2025-02-24
Promised by
2027-07-31
Promised amount
2.7 c/kWh
Current status
stated

The claim, verbatim

Company has access to electricity at Odessa Facility at cost of approximately 2.7 cents per kilowatt-hour through at least July 2027

Source (primary)

Cipher Mining 10-K filed 2025-02-25 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “pursuant to which we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Cipher Mining 10-K filed 2025-02-25

Quote: “pursuant to which we have access, until at least July 2027, to a cost of electricity of approximately 2.7 c/kWh”

View cached copy (2026-08-31)Live source ↗